University of Wisconsin Student Athlete Performance Center

The work was done in stages between football seasons, but the transformation is now complete, and all of our student athletes are the winners.
The work was done in stages between football seasons, but the transformation is now complete, and all of the student athletes are the winners. SportsPLAN Studio completed the programming phase in April, 2011, and we worked with Berners Schober and VOA to complete the design and bid documents.
The lower level of the McClain Center Field House has been completely reconfigured to provide locker rooms and team lounges for UW Football, Soccer and Track, a sports medicine center, a Human Performance Lab and a supplemental strength and conditioning center. The indoor practice space is getting new turf, a new roof, new lighting and a new exterior facade along Badger Way.
Phase Three improvements added a 32,000 square foot academic center, a new strength and conditioning center in Camp Randall Stadium, team meeting rooms, press conference and hospitality spaces and a dazzling three story lobby and display gallery, creating a new image for the UW Athletics.
Services
Feasibility StudyProgramming
Master Planning
Design Consulting
Equipment Specifications
Operational Planning
Program Features
Indoor Practice Field ReconstructionNew Locker Rooms and Amenities
32,000 SF Academic Center
20,000 SF Strength and Conditioning
Sports Medicine and Hydrotherapy
Human Performance Lab
Wrestling Practice Expansion
New Stadium Scoreboard
Lobby and Display Gallery/Hospitality
Project Manager: | Joel Leider |
Architect of Record: | Berners-Schober |
Design Architect: | VOA |
Project Cost: | $76 million |
Completion Date: |
Phases 1 & 2: 2012 |